JOHN HOLLAND/ARTC – VICTORIAN SUPER POSSESSION

SUMMARY

Brunton Engineering & Construction was engaged by John Holland Rail Services for the replacement of five bridge decks over 48 hours during the March 2018 ARTC ‘super-occupation.

SUMMARY

Brunton Engineering & Construction was engaged by John Holland Rail Services for the replacement of five...

CLIENT

JOHN HOLLAND/ARTC

REQUIREMENTS

Requirements Here

SHARE THIS

Careful staging was required to ensure multiple crews of crane operators, riggers, labourers, concrete cutters and supervisors were able to remove and replace the bridges, enabling John Holland Rail Services to implement track works before the required handover.

Project highlights included:

  • Mobilisation of all site personnel and equipment ready for works commencement
  • Careful staging of multiple crews
  • Efficient completion of installation works, allowing handover of bridge locations to track reinstatement crews.